How time flies... we are going to finish our renovating soon. It was a tough job for the aircon guys to pull our compressor through the window. Luckily, they managed to do it by the end of the day and the system is working fine. The weekend was spent scrubbing and wiping the floors and walls. Also went ikea to make a list of things to buy, now that we are on a tight budget. We are only left with minor stuff to be done.
1.) Few pieces of glass to be delivered and fixed in various spots in the house. done on 04/09
2.) Wallpaper for the TV console. done on 01/09 UPDATE on 06/09: wrong wallpaper (pending rectification) UPDATE: done on 13/09
3.) Carpentry works (door stopper on main door, drill holes for consoles) done on 06/09
4.) Lights bulbs to be replaced at kitchen and display cabinet done on 06/09
5.) Buy and install doorbell done on 06/09
6.) WIW done on 22/09
7.) Chip on laminated platform done on 03/09
8.) Scratches on glass on platform done on 12/09
9.) Gas connection done on 06/09
10.) Final Paintworks done on 22/09
Sunday, 31 August 2008
Saturday, 23 August 2008
Updates
This week carpentry works continued. The people came to clear the haulage and the whole place looks neater. Someone came to take measurements for the glass pieces but the plumber was nowhere to be seen. 3 hrs later, he still failed to show up. Got to fix another day with him again to help us with the bathroom accessories. Labeled a few hollow tiles and checking what stuff needs rectifying.
Friday, 15 August 2008
Heaven (Lights) & Earth (Flooring)
Work was progressing this week. Lights were up on Thursday and flooring finished by today. They even put up the hood and sink in the kitchen.
Some minor issues:
1.) Wrong walkway down light installed rectified on 18/08
2.) Altar table height too short rectified on 30/08
3.) Feature wall tear rectified on 30/08
4.) Curtain tracking too close to window rectified on 18/08



Some minor issues:
1.) Wrong walkway down light installed rectified on 18/08
2.) Altar table height too short rectified on 30/08
3.) Feature wall tear rectified on 30/08
4.) Curtain tracking too close to window rectified on 18/08